The Taube Family Carriage House at 2200 Broadway in Redwood City, three stories of tan stucco with a blue Victorian house beside it

The project

Metallic panels and EIFS trim for a Redwood City museum.

BayStone made the metallic spandrel panels, the pre-coated EIFS window trim and the lettered sign panels for the Taube Family Carriage House and Automobile Museum at 2200 Broadway in Redwood City. We drew and built them for the plastering contractor, Patrick J. Ruane, Inc. The San Mateo County Historical Association opened the museum in November 2026.

BayStone's work
Dryvit Fedderlite spandrel panels with a Reflectit metallic finish, pre-coated EIFS trim and sign panels
Panels
13 Fedderlite panels; the 11 large ones are about 56 inches tall and 9 to 10 feet long, each with a 30-inch round
Drawings
About 100 sheets
Years
2024 to 2025
Location
2200 Broadway, Redwood City, CA
Building
Three-story museum, about 15,000 square feet
Architect
Adolph S. Rosekrans, Inc.
General contractor
Gonsalves & Stronck Construction Co.
Plastering contractor
Patrick J. Ruane, Inc.

Panels

Metallic spandrels

Stepped parapet and arched end windows; the arched surrounds are pre-coated EIFS trim from our shop

The Fedderlite panels fill the band between the two tall window walls on the north, east and west sides. Each one is EPS foam, 2 inches thick, with Fedderlite channels in the back, meshed and base-coated, and finished in Reflectit with a 30-inch round in its face. Eleven large panels and two smaller ones fill the band.

Why panels

Shop-applied finish

Building corner under the Theatre District arch; the trim, water table and arched heads came pre-coated from our shop

Reflectit is a metallic finish applied with the panel flat on a table. Finishes like it generally can't be applied on a wall in the field, so the spandrels were finished in our shop and shipped ready to set between the window frames.

Trim

Arches and water table

Sign panel lettered Taube Family Carriage House and Automobile Gallery, set among arched surrounds and grid windows

The field walls are EIFS, and the trim on them came from our shop already meshed and base-coated.

  • Arched heads for the 12 arched windows
  • Window heads, jambs and sills, including jambs with reveals
  • A water table along the base, with its corners and end pieces
  • Door jambs, bullnose corners and window trim
  • Starters at the base and top of the walls
  • The pediment panel with a round, at the top of the north wall

Timeline

2024 to 2025

One of the three name sign panels beside arched windows at the corner

Production ran from March to June 2025.

  1. June 2024

    Start

    The plastering contractor took on the exterior cladding, and our drawings began.

  2. December 2024 to March 2025

    Drawings

    The drawing set was approved in March 2025.

  3. March and April 2025

    Trim

    The first EIFS trim went into production on March 14: starters, then the window and door pieces, the water table and the arched heads.

  4. April and May 2025

    Sign panels

    The three name panels and the address panels were made.

  5. June 2025

    Fedderlite panels

    The spandrel panels went into production.

  6. December 2025

    Finished

    The building was photographed complete.

  7. June 2026

    Award

    Patrick J. Ruane, Inc. won a Wall & Ceiling Alliance Construction Excellence Award in the EIFS category for the building.

  8. November 2026

    Opening

    The museum opened.