The Folsom medical office building: light EIFS panels above a gray base, with a Cleopatra Reflectit frame around the glass at the end

The project

Metal-stud panels for a Folsom medical office building.

BayStone modeled, drew and made 231 prefabricated metal-stud panels with an EIFS finish for a three-story medical office building in Folsom, California. The panels clad all four sides of the building and the Linac, in six Dryvit finishes, and went up from February to May 2026.

BayStone's work
Pre-construction and prefabricated metal-stud panels with an EIFS finish
Panels
231, on all four sides of the building and the Linac
Finishes
Six Dryvit finishes, including a copper-colored Reflectit on the frames around the glass and on the tall east walls
Drawings
About 1,700 sheets
Years
2024 to 2026
Location
Folsom, CA
General contractor
The Boldt Company
Panel installer
Archuleta Constructors

Pre-construction

Modeled first

3D views of the metal-stud framing of corner panel N1-5, with its diagonal straps and bridging

BayStone built a Revit model of the panel framing and laid out the panel joints on every elevation. Each panel has its own framing ticket and its own EIFS ticket: about 600 framing sheets and about 680 EIFS sheets for the 231 panels. The termination details, at about 135 sheets, cover where the panels meet the windows, the doors, the canopies, the roof and the ground.

Mockup

Built first

Mockup wall elevation with the panels color-keyed by finish around a storefront, a curtain wall and a sunshade

A mockup wall, with its framing, panels, a window opening and the flashings, was drawn and built in the summer of 2025, before production started.

Panels

231 panels

Light and gray vertical panel bands at the end of the building, beside the copper-colored frame around a glass wall

Each panel was framed with metal studs, sheathed and waterproofed, then meshed, base-coated and finished in our shop. The finishes are Dryvit's Natural White, Tattletale, Dark Chocolate and Anthracite Coal Sandpebble Fine, Everest Terraneo, and Cleopatra Reflectit, the copper-colored metallic on the frames around the glass and the tall walls on the east side.

Why panels

Shop-built walls

The end wall at the left, with the open framed floors running along the building

Production ran from October 2025 to April 2026, alongside the steel frame and floors going up on site. Set in place, the panels closed in the building quickly.

Install

Set by crane

A trailer of panels waits by the building as lifts and the crane work along the gray wall

The panels hang from pins and slotted plates welded to the steel frame. They were set by crane from February to May 2026, with the Linac in May.

Timeline

2024 to 2026

3D views of the metal-stud framing of corner panel N1-5, with its diagonal straps and bridging

Pre-construction started in 2024. The panels were made in 2025 and 2026 and installed in the first half of 2026.

  1. January 2024

    Panel joints

    The first panel joint layout for the building.

  2. August 2024

    Termination details

    The first details for the panel edges and openings.

  3. summer 2025

    Mockup

    The mockup was drawn and built.

  4. October 2025 to April 2026

    Production

    The first panels were framed on October 16, 2025, and the last on April 8, 2026.

  5. February to May 2026

    Delivery and install

    The panels shipped from late January to May 1, 2026.

  6. October 2026

    Near finish

    The building was photographed with its panels in place on October 6, 2026.