Rainbow Hotel Casino facade at night, with the Rainbow Hotel and Bimini Buffet signs lit

The project

Casino facade renovation at the Rainbow Hotel Casino, West Wendover.

At the Rainbow Hotel Casino, 1045 Wendover Boulevard in West Wendover, Nevada, BayStone delivered a turnkey casino facade renovation. We surveyed, designed, permitted, fabricated and rebuilt the exterior as general contractor, with the owner's group, Peppermill Casinos, running the project for the owner.

BayStone's work
Turnkey facade renovation, acting as general contractor
Products
Prefabricated metal-stud cornice panels, Baystone wainscot and 2-inch EIFS finished in Dryvit Sandpebble
Scale
About 900 linear feet of cornice, about 360 linear feet of wainscot and about 9,500 square feet of EIFS
Drawings
About 400 sheets, including the permit set and the panel and component shop drawings
Years
Concept design in 2021, construction from fall 2024 into early 2025
Location
Rainbow Hotel Casino, West Wendover, NV
Owner group
Peppermill Casinos ran the project for the owner
Structural engineer
Sawtooth Structural Engineering
On site
About three months

The work

Full rebuild

The job ran in sequence: cornice panels built in the shop first, then each side of the building stripped, re-sheathed and finished in turn. BayStone carried the whole facade, not one trade.

Scope

Turnkey

Hotel entrance tower before the facade work

We did the field surveys, prepared the design and the permit submittal package in house, and fabricated the panels in our shop. As general contractor we handled the demolition and brought in the signage, electrical, plastering and sealant trades. We also coordinated lighting, scaffolding, fencing and cranes around the building, including pedestrian access.

Design

Wainscot to cornice

Tower 2 isometric and elevations

The transition from base to parapet was part of the design.

  • Baystone wainscot at the base for durability
  • EIFS across the middle of the facade
  • Highly decorative cornice panels at the parapet and on the towers

Installation

Ready before demolition

A cornice panel rising to the parapet

Once the permit was issued we verified dimensions in the field and built panels, timed so an elevation's panels were ready before its demolition began. Each elevation was then stripped, re-sheathed with DensGlass and covered with a water-resistive barrier, and the panels flew into place by crane.

Products

What we built

Pale panel with raised rectangular and rounded relief, crated and strapped on a pallet in the shop

Elements and systems for the Rainbow facade:

  • Prefabricated metal-stud cornice panels, about 900 linear feet
  • Tower cornice panels
  • Towers
  • Balustrade
  • Pilasters
  • Entries
  • Registration tower
  • Baystone wainscot, about 360 linear feet, with left and right return pieces
  • DensGlass sheathing
  • Water-resistive barrier
  • 2-inch EIFS, about 9,500 square feet
  • Dryvit Sandpebble finish in Sandlewood Beige
  • Sealants

On the job

2021 to 2025

Drone view of a finished lit elevation

Concept design, 2021. Design concepts for the new facade were developed and reviewed with the owner's group.

Our project team kept daily reports from mobilization to the last seam.

  • About three months on site, through the winter
  • Panels ready before each elevation came down
  • Signage, lighting, scaffolding, fencing and cranes coordinated by us
  • Structural calculations by Sawtooth Structural Engineering
  1. May-June 2024

    Field surveys

    We surveyed the existing building and documented it in photographs.

  2. June 2024

    Contract

    The work went under contract with completion targeted before the holidays.

  3. August-September 2024

    Permit set and fabrication

    We prepared the permit set and shop drawings, with the structural engineer, and the first elevations' panels went into production.

  4. September 30, 2024

    Mobilization

    We mobilized on site, with scaffolding going up on the north elevation on October 1 and tower framing beginning in October.

  5. October-December 2024

    Panels flown

    Cornice panels went up by crane from late October, with the scaffolding and fencing moved ahead of each phase.

  6. December 2024

    Entries finished

    The entry finishes were done and the scaffolding came down at the casino by December 18.

  7. January 2025

    Caulking

    Exterior caulking was released in early January 2025.