Courtyard of 200 Linden Avenue in South San Francisco, with lawn, rounded seats and planting beds between the wings

The project

Prefabricated EIFS panels for an eight-story South San Francisco building.

BayStone made the dark metallic frames around the window bays at 200 Linden Avenue in South San Francisco: about 140 Dryvit Fedderlite panels with a Reflectit finish. We also made the pre-coated EIFS window trim, starters and balcony fascia that Patrick J. Ruane, Inc. set in the field walls.

BayStone's work
Dryvit Fedderlite panels with a Reflectit metallic finish, and EIFS shapes coated in the shop
Panels
About 140, set around the windows
Drawings
About 310 sheets, including a ticket for every panel
Years
2020 to 2021
Location
200 Linden Avenue, South San Francisco, CA
Building
Eight stories, with retail, three levels of parking and five floors of condominiums, 97 units
Plastering contractor
Patrick J. Ruane, Inc.
Awards
2023 Wall & Ceiling Alliance Construction Excellence Awards, Project of the Year (Exterior), EIFS, and Residential / Lodging Exterior, to Patrick J. Ruane, Inc.

Panels

Window-bay frames

Dark metallic Reflectit frames around the window bays at the street corner, about 140 panels in all

The frames are made of tall jambs, up to almost 12 feet, with sills and bands across each bay and caps along the parapet. Each panel is EPS foam with Fedderlite channels set into the back, meshed and base-coated, skimmed smooth, color-primed and finished with two coats of Reflectit.

Why panels

Shop-applied finish

Edge of a metallic frame against white EIFS walls and windows built by other trades

Reflectit is a metallic finish applied with the panel flat on a table. Finishes like it generally can't be applied on a wall in the field, so the frames were finished in our shop before they shipped.

The panels are also light and quick to hang. Each one arrived finished and went up on clips.

Fit

Three batches

A panel corner with its clip and the field-measured dimension written on the wall beside it

The frames meet brick, windows and white EIFS walls built by other trades. The plaster crew measured the bays on the building in three batches in fall 2020, and each panel was drawn to those measurements before it was made.

Components

EIFS trim

Eight-story corner of brick and white walls, the dark window-bay frames rising up the tower

Alongside the panels, we made the EIFS pieces the plaster crew set in the field walls, coated before they shipped.

  • Window headers, jambs and sills, in 1-inch and 2-inch window packs
  • Starters, notched-back and sloped-top
  • Balcony fascia

Timeline

2020 to 2021

200 Linden metallic frames going up beside the scaffold with a lift below

Production ran from July 2020 to February 2021.

  1. summer 2020

    Mockup

    Mockup panels in EIFS and Reflectit were drawn in June and July and made in August.

  2. fall 2020

    Field measuring

    Three batches of field dimensions came back, and the panel drawings were revised to match.

  3. November 2020 to January 2021

    Panels

    The first panel order went into production on November 3, and panels shipped through January 20, 2021.

  4. February 2021

    Installation

    The frames were going up on the street side by February 10.

  5. June 2021

    Finished

    The building was photographed complete.

  6. 2023

    Awards

    Patrick J. Ruane, Inc. won three Wall & Ceiling Alliance Construction Excellence Awards for the building.