The two-story entrance bay in black corrugated panels, with its canopy, logo and glass storefront

The project

Corrugated metallic panels for a private car museum in Irvine.

BayStone made 72 corrugated panels with a black metallic finish for a private car museum in Irvine, California. They clad three bays on the front of an existing tilt-up building and shipped in August and September 2024.

BayStone's work
Corrugated Dryvit Fedderlite panels with a Reflectit metallic finish, finished in our shop
Panels
72, the largest about 9 feet wide and 12 feet tall
Bays
The two-story entrance, with 48 panels, and one bay at each end, with 12 each
Drawings
About 140 sheets
Years
2023 to 2024
Location
Irvine, CA
General contractor
Pacific Design Directions

Panels

72 panels

Ribbed Tricorn Black panels run up past the roll-up door to the top of the wall, beside a young magnolia

The panels clad the two-story entrance in the middle of the front wall, a roll-up door bay at one end and a bay with a service door at the other. Each panel is 1-pound EPS with Dryvit's Genesis base coat and mesh, a smooth Skimit coat, a color prime and two coats of Reflectit in Sherwin-Williams Tricorn Black.

The ribs run vertically, and the panels return around the windows, the doors and the top of the wall. Some are L-shaped to fit around a window, and some have openings for the wall lights.

Why panels

Shop-finished

Vertical ribs on the entrance bay catch the light above the canopy and storefront

Reflectit is a specialty finish that generally can't be applied in the field. Every panel was finished in our shop before it shipped. Fedderlite panels are also light: these hang on Dryvit hat channels and Z-clips over the sheathed wall framing.

Fit

Scanned walls

Scan heat map of the existing tilt-up walls showing how far each is out of plumb, up to about 3 inches

The tilt-up concrete walls were already standing, and they were not plumb. The walls were laser scanned in April 2024, and our scan analysis mapped how far each wall leaned, up to about 3 inches in places. The panel sizes and the clip layout were drawn to the scan, and the window openings and the furring depth at the entrance were measured on site.

Details

Canopy and lights

Panels return around the canopy, wall lights and logo; every edge that meets the glass is a sealant joint

The entrance bay carries a steel canopy, wall lights and the building's logo. The panels fit around each of them, and every panel edge meets the doors, the windows and the walls beside them at a sealant joint.

Timeline

2023 to 2024

Ribbed Tricorn Black panels run up past the roll-up door to the top of the wall, beside a young magnolia

The panels were drawn from October 2023 and made in the summer of 2024.

  1. October 2023 to February 2024

    Submittals

    The first panel drawings went to the contractor for review.

  2. April 2024

    Scan

    The existing walls were laser scanned and checked for plumb.

  3. May 2024

    Corrugation design

    The rib profile was set, and each panel was drawn to the scan.

  4. June to August 2024

    Production

    The first panels went into fabrication on June 19, and the last were finished in late August.

  5. August and September 2024

    Delivery

    The end bays shipped on August 19 and 26, and the entrance bay on September 5.

  6. October 2024

    Finished