Hotel tower at Hard Rock Hotel & Casino Sacramento, with BayStone's metal-stud panels between the window bays

The project

Metal-stud panels for the Hard Rock hotel tower.

BayStone built the exterior wall panels for the hotel tower at Hard Rock Hotel & Casino Sacramento at Fire Mountain: about 265 pilasters and spandrels and 24 parapet panels, framed and finished in our shop. KHS&S set them on the building.

BayStone's work
Panel drawings, fabrication and Sto finish
Panels
About 265 pilasters and spandrels, and 24 parapet panels
System
Sto StoTherm ci and Sto Gold Coat on 5/8-inch DensGlass over metal studs
Years
2018 to 2019
Location
3317 Forty Mile Road, Wheatland, CA
General contractor
Moorefield Construction and Yates Construction, joint venture
Panel framing engineer
Lochsa Engineering
Customer and installer
KHS&S

Panels

Pilasters and spandrels

Orange pilaster panels and tan spandrel panels between the windows

The tall orange pilasters run between the window columns from level 2 to level 5. The tan spandrels sit under the windows from level 3 to level 6, and parapet panels finish the roofline.

Build

Panel build-up

Panels on tables across the shop floor, each one built and checked on its table

Each panel is a metal-stud frame sheathed in 5/8-inch DensGlass, with Sto Gold Coat as the air and water barrier and StoTherm ci insulation and finish over it. Lifting coils in the studs give the crane its pick points.

Each spandrel was sized to its window opening, with a 5/8-inch sealant joint, and a Sto floor-line detail meets NFPA 285.

Why panels

Built in parallel

Pilaster panels set on the tower's upper floors while the frame below is still open

While the tower's concrete frame was going up, we were framing and finishing its walls off site. The panels arrived finished and went up by crane to close the building in.

Every panel was built and checked on a shop table, and one panel type repeats 110 times.

Timeline

2018 to 2019

Tall pilaster panel on the crane hook beside the tower, its upper floors still open

Drawings started in late 2018, and the hotel opened less than a year later.

  1. November 2018

    Drawings

    The panel shop drawings and Sto details were issued.

  2. December 2018

    Final set

    The final panel drawings were issued for production.

  3. January to February 2019

    Parapet

    The parapet panels followed, then an as-built parapet set for the 24 panels.

  4. 2019

    Production and install

    We built the panels, and KHS&S set them by crane as the tower went up.

  5. October 30, 2019

    Opening

    Hard Rock Hotel & Casino Sacramento at Fire Mountain opened.