1640 Broadway among the towers of downtown Oakland, its upper levels clad in prefabricated EIFS panels

The project

High-rise walls, built on the ground.

1640 Broadway is a high-rise in Oakland, California. BayStone drew, built and delivered prefabricated light-gauge steel-framed EIFS panels for its upper levels. KHS&S installed them. The panels are finished in a Sto system and shipped as complete wall sections.

BayStone's work
Prefabricated steel-framed EIFS panels
System
Sto, with Sto Gold Coat air and water barrier, EPS insulation, mesh and basecoat, and a Sto textured finish
Framing
6-inch, 16-gauge, G-90 galvanized steel studs, welded
Panel size
Up to and over nine feet wide, shipped by wide load
Years
2016 to 2018
Location
1640 Broadway, Oakland, CA
Customer and installer
KHS&S
Framing engineer
Devco Engineering

The work

Upper levels

The panels go on the high-rise's upper floors, where working from the ground matters most. Each one is framed in steel, sheathed, insulated and finished in our shop, so the crew on the building sets a finished wall section instead of building it in the air.

BayStone worked to Sto details throughout, and KHS&S installed the panels in the field.

System

Full Sto system

Finished EIFS panels lined up in a row in the shop

Every panel is a complete wall:

  • Light-gauge steel frame of 6-inch, 16-gauge, G-90 galvanized studs with 12-gauge track
  • Welds at every stud-to-track connection, with a reinforced top track
  • Gypsum sheathing
  • Sto Gold Coat air and water barrier
  • EPS foam insulation
  • Mesh and basecoat
  • Sto textured finish

Elements

Lift-ready panels

A panel hanging from the crane over the street, with neighboring towers behind

- Prefabricated light-gauge steel-framed EIFS wall panels - Wide wall panels, delivered complete - Welded steel framing with lifting eyes for hoisting - Base-of-panel flashings, Sto wedges and weeps - Intermediate-slab caps at end studs - Numbered panels, each with a ticket drawing - Trucking braces and a trucking plan for wide-load delivery

Pre-construction

Engineered first

Rear of a panel with twelve keyed parts, including 12-gauge track, 16-gauge studs, strongback, lifting coil, Sto wedge with weep, Densglas and Goldcoat

Framing was designed by Devco Engineering, and each panel was drawn with its own ticket. We built a mockup, wrote a quality-control plan, and reviewed the details with Sto before production. Panel widths on the upper levels set the vertical control-joint locations on the levels below, so the layout was worked out in advance.

Production and delivery

Wide loads

Crew unloading a flatbed of finished panels and foam shapes, one panel already hanging on its chains

Welds, screws and waterproofing were inspected and reported, along with Sto's own review. Because panels run up to and over nine feet wide, we planned each delivery as a wide load, with the loading order matched to the order the installer needed them.

On the job

Scope to finish

Installers guiding a panel into place

We don't drop panels at the curb. We stay with the work from price to delivery.

Throughout, our project team worked with KHS&S, Devco Engineering and Sto on details, drawings and delivery order.

  • Pricing to deliveries across two years
  • Sto details followed from drawings through the mockup
  • Panels engineered with the framing engineer
  • Inspected welds, screws and waterproofing
  • Wide-load deliveries planned panel by panel
  1. October 2016

    Pricing

    We priced the panels and proposed the foam thickness for the Sto system.

  2. September 2017

    Drawings

    Panel drawings were finished at the end of September, and the quality-control plan started in early October.

  3. December 2017

    Submittals

    The submittal package was finished and the panel drawing issued in mid-December. The framing engineer's drawing review followed in January 2018.

  4. February 2018

    Pre-installation meetings and Sto review

    We met with the installer before installation and held the Sto review in late February.

  5. mid-2018

    Deliveries

    Loading and installation orders were circulated for the first delivery in June 2018, and panels shipped in sequence by wide load.